SMMT says UK depot charging grants welcomed, but grid connection remains a bottleneck

SMMT said the UK Department for Transport's new round of the Depot Charging Scheme is welcome, but grid connections and approvals are still slowing the conversion of heavy truck and bus depots.

· 2 min read · AutoMusic Editorial
Heavy truck charging at a depot, no branding or license plates

SMMT said in a statement on Oct 29, 2026 that the UK Department for Transport (DfT)'s new round of the Depot Charging Scheme is a positive step towards removing one of the main barriers to decarbonising heavy trucks, namely reliable, suitable charging infrastructure. It also noted that grid connections and legal approvals will still slow depot upgrades.

Scope: UK; SMMT commentary of Oct 29, 2026; depot charging build-out for zero-emission heavy truck and bus operators. Metrics: policy positions and list of barriers; no quantitative metrics.

SMMT says that for operators, switching to zero-emission heavy trucks and buses is not just about buying new vehicles; depots also need sufficient power capacity, charging equipment, space and operational flexibility. According to SMMT, grants can help businesses get started and test practical approaches, and drive collaboration among hauliers, bus operators, infrastructure providers, energy companies, local authorities and manufacturers.

SMMT identifies two main types of barriers:

BarriersSMMT's view
Grid connectionWhere the grid is weak or several users compete for power, securing a connection with enough capacity can take years; grid reinforcement must be planned together with investment in chargers and vehicles
Legal and approvalsDepot upgrades usually involve planning permission, lease changes, construction approvals and negotiations over access and land use, and often take longer than expected

SMMT argues that without more coordinated grid planning, publicly funded projects may still face long delays; it advocates sharing lessons from depot decarbonisation to inform future projects.

Analytically, the grants address capital expenditure, while grid connection scheduling and approval timelines still have to be progressed separately. This does not tell us how many depots a new round of grants will help convert.

Reading note: published by SMMT on Oct 29, 2026, this is commentary from an industry body, not a DfT policy announcement. The funding, application deadline and number of depots covered by the new round of the Depot Charging Scheme have not been announced, and no comparison-period data is available.