On Nov 19, Germany's Federal Ministry of Transport announced that Autobahn GmbH has launched a competitive tender for truck fast charging at 227 serviced rest areas. The tender is split into 5 lots and covers planning, construction and operation. Contracts for 124 unserviced rest areas were awarded in Jun 30. This page covers both tender rounds: site and charge-point numbers, award dates, the third Cleanroom manufacturer forecast published the same day, the construction timeline of the HoLa pilot project, and two policy milestones: toll exemptions and the EU's AFIR.
German motorway service areas come in two types: staffed service areas with fuel stations and catering, and unstaffed rest areas with only parking and toilets. The federal government is tendering the truck fast-charging network in two batches along these lines, with all sites on federally owned land.
| Non-commercial service areas | Commercial service areas | |
|---|---|---|
| Site | 124 locations | 227 locations |
| Status | Awarded 2026-06-30, under way | Prequalification opens 2026-11; shortlisted bidders then invited to quote |
| Lot | 5, about 25 sites each | 5, each with about 45 locations, including large and small stations |
| MCS charging points | 447 | 1251 |
| CCS charging points | 389 | 1869 |
| Average per station | About 6.7 | About 13.7 |
| Construction / operation period | Not disclosed | To be completed within 5 years, subject to timely grid connection; operated for 8 years, extendable by 4 years |
| Awardee | eliso Voltix, autostrom.plus, Electric Mobility Infrastructure Deutschland, STRA-loaded consortium, E.ON Drive and mblty consortium | Award targeted for late 2027 to early 2028; evaluation weighting: price 70%, quality 30% |
The Cleanroom report, commissioned by Germany's Federal Ministry of Transport and compiled by NOW GmbH, covers truck makers' planned sales over the coming years and the strategic direction behind them, with editions published in 2022, 2024 and 2026. The report says that, compared with the 2024 forecast, the uptake of zero-emission trucks has been delayed by up to five years. Manufacturers participating in this edition account for about 75% of the German and European heavy truck market above 12 tonnes.
| Topic | Manufacturer's account |
|---|---|
| Adoption pace | Zero-emission trucks will become widespread, but more slowly than expected in the 2024 survey; by 2035, BEV trucks will approach 50% of new heavy trucks over 12 t in Germany, replacing diesel as the dominant powertrain |
| Total cost | Under certain conditions and with enough mileage, electric trucks already make economic sense. Most manufacturers expect BEV trucks to reach total cost parity with diesel trucks in all use cases by 2030 |
| Prerequisites | Accelerate public charging and hydrogen refueling infrastructure and support depot charging |
| Charging mix | Many manufacturers expect about two-thirds of charging sessions at depots and one-third at public stations; by energy volume, some estimate a 50/50 split |
| Other powertrains | Fuel cells, hydrogen combustion engines and biogas as supplements; series production of hydrogen powertrains pushed back to 2029 or later |
| Competition | European manufacturers take Chinese rivals very seriously and demand a level playing field |
Coordinated by the Fraunhofer Institute for Systems and Innovation Research (ISI) and P3, HoLa is Germany's first public megawatt charging demonstration project, with 12 CCS and 7 MCS charging points and a combined grid connection of 8.7 MW. The project ended on Jan 15, 2027, and a 33-page final report was published in Nov 19.
| Item | Content |
|---|---|
| MCS field test | About 0.7 MW, close to 1 MW on site |
| Pilot operation | 10 electric trucks, about 520,000 km and more than 2,000 charging sessions from 2024-05 to 2026-10 |
| Standard | MCS becomes the unified standard across all truck power levels, including depot and overnight low-power charging |
| CCS | Phase out gradually along a coordinated transition path, keeping existing vehicles usable during the transition |
| Process | Grid connection, sites and permits often take years and must start ahead of charging demand |