German construction group STRABAG AG bought a 50% stake in R:loaded SE from econX. Capital. eLoaded holds the other half, and the price was not disclosed. On Jun 30, 2026, the three companies' consortium won Lot 4 of the federal truck fast-charging network. The second tender round covers 227 sites with service areas and about 3,300 charging points, and is scheduled to launch in month 11. This page sets out the published figures in four parts: the transaction, Lot 4, the winners of the five lots, and the second tender round.
The buyer's press release was issued on November 13; the seller's press release gave the closing date. Neither disclosed the price or R:loaded's revenue.
Commissioned by the Federal Ministry of Transport, Autobahn GmbH awarded contracts on Jun 30, 2026 for the planning, construction and operation of 124 unserviced rest areas in five lots. The consortium of STRABAG, eLoaded and R:loaded is called STRA-loaded.
Each of the five lots went to a single winning bidder, and every contract covers planning, construction and operation. The winners' shareholders include construction and concession groups, energy companies and service area operators.
| Lot | Awardee | Shareholders or members | Site | Charging points |
|---|---|---|---|---|
| 1 | eliso Voltix Charging | Part of France's VINCI Concessions; eliso acquired in 2022, Voltix set up by VINCI in 2023 | 25 | Not disclosed |
| 2 | autostrom.plus | Led by Drees & Sommer, Enercity, Q1 Energie; other members include Pohl Group, RheinEnergie and others | 24 | 148 |
| 3 | Electric Mobility Infrastructure Deutschland | German subsidiary of Engie Vianeo, part of France's Engie Group | 26 | Not disclosed |
| 4 | STRA-loaded consortium | STRABAG、eLoaded、R:loaded | 25 | 140 |
| 5 | E.ON Drive & mblty consortium | E.ON Drive Infrastructure; mblty is a brand of motorway service operator Tank & Rast | 24 | 195 |
| Construction group | Tenders | Operator | Relationship |
|---|---|---|---|
| VINCI | Truck fast-charging network, lot 1, 2026 | eliso Voltix Charging | Group subsidiary |
| HOCHTIEF | Two regional lots of the passenger car Deutschlandnetz, 2023 | EWE Go HOCHTIEF Ladepartner | Joint venture set up for the project by Hochtief and EWE Go, a subsidiary of energy company EWE |
| STRABAG | Truck fast-charging network, lot 4, 2026 | R:loaded | Consortium partner at bidding; STRABAG has held 50% since 2026-09-30 |
Sites with service areas were not included in the first round. Autobahn GmbH published a project prospectus in month 9; the conditions below come from electrive's report on that prospectus and may change once the tender documents are formally published.
Lot 4 has 140 charging points, 16.7% of the 836 in the first round and 3.3% of the roughly 4,200 across the whole network.
In the second round, each lot has about 45 sites, averaging about 650 charging points, or 4.6 times the 140 in lot 4.
The federal government has allocated around EUR 1 billion for the entire network, which works out to roughly EUR 240,000 per charging point across about 4,200 points. Grid connection costs are borne separately by the federal government, and this per-point average does not represent the contract value of any individual lot.
| Figures | Scope | Source |
|---|---|---|
| 50% | R:loaded SE stake acquired by STRABAG AG; the remaining 50% is held by eLoaded | STRABAG 2026-11-13;electrive 2026-11-14 |
| 2026-09-30 | Closing date | econX. capital press release |
| 25 sites / 140 units | Rest areas without services and truck charging points in lot 4 | STRABAG 2026-11-13 |
| 2030 / mid-2034 | Planned completion of lot 4; end of R:loaded operating contract | STRABAG 2026-09、2026-11-13 |
| 124 sites / 836 units | Sites and charging points in the five first-round lots; MCS 447, 400 kW CCS 157, 100 kW CCS 232 | Federal Ministry of Transport 2026-07-02 |
| 195 / 148 | Charging points in lot 5 and lot 2 | electrive 2026-07-01 |
| Approx. 350 sites / approx. 4,200 points | Planned sites and charge points of the federal truck fast-charging network; around EUR 1 billion in federal funding | Federal Ministry of Transport 2026-09-15 |
| 227 sites / approx. 3,300 units | Round two sites with service areas: about 1,300 MCS plus about 2,000 CCS | electrive 2026-09-18 |
| 8 years + 4 years | Second-round contract term and maximum extension | electrive 2026-09-18 |
| 70% / 30% | Price and quality weighting in second-round evaluation | electrive 2026-09-18 |
| Approx. EUR 4 billion / approx. EUR 20 billion | Annual output of STRABAG AG's transport infrastructure business and of STRABAG SE | STRABAG 2026-11-13 |