Germany · Electric heavy trucks · Public charging Announced by STRABAG Nov 13, 2026

STRABAG buys 50% stake in charging operator R:loaded: Lot 4, 25 sites with 140 truck charging points, operated until mid-2034

German construction group STRABAG AG bought a 50% stake in R:loaded SE from econX. Capital. eLoaded holds the other half, and the price was not disclosed. On Jun 30, 2026, the three companies' consortium won Lot 4 of the federal truck fast-charging network. The second tender round covers 227 sites with service areas and about 3,300 charging points, and is scheduled to launch in month 11. This page sets out the published figures in four parts: the transaction, Lot 4, the winners of the five lots, and the second tender round.

STRABAG press release · 2026-11-13 econX. capital press release German Federal Ministry of Transport (BMV) · 2026-07-02 / 09-15 electrive.net · 2026-07-01 / 09-18 / 11-14 STRABAG press release · 2026-09
R:loaded stake acquired by STRABAG
0%
Seller: econX. Capital; remaining 50% held by eLoaded
Lot 4 truck charging points
0 items
25 rest areas without service facilities
Charging points in five lots of round one
0 items
124 sites, awarded 2026-06-30
Second-round tender sites
0 locations
With service area; about 3,300 charging points
01 / transaction

Deal terms and size of both parties

The buyer's press release was issued on November 13; the seller's press release gave the closing date. Neither disclosed the price or R:loaded's revenue.

Deal at a glanceSTRABAG AG acquires stake in R:loaded SE · press releases from buyer and seller
Stake acquired
50%
Buyer: STRABAG AG (Cologne)
Seller
econX. Capital
Oliver Nee's holding company
Other 50% shareholder
eLoaded
Former shareholder; technical partner for lot 4
Closing date
2026-09-30
Seller press release; buyer announced Nov 13
R:loaded founded
Year 2022
Headquartered in Erkner, near Berlin
First fast-charging station
9 charging points
Leipheim, initial capacity, up to 600 kW
Source: STRABAG press release 2026-11-13; econX. capital press release; electrive.net 2026-11-14
R:loaded shareholding: STRABAG 50%, eLoaded 50%
Diagram · shareholders before and after the deal
Pre-transaction econX. Capital 50% eLoaded 50% R:loaded SE After the deal (closed 2026-09-30) STRABAG AG 50% eLoaded 50% Management: Oliver Nee steps down; Anja Birkenfeld and Paul Steinbacher take over
Source: STRABAG press release 2026-11-13; electrive.net 2026-11-14; econX. capital press release
▸ The seller says R:loaded was founded by ALMON Capital and FS Holding in 2022. A majority stake in the Leipheim site project company was previously sold to an investor and falls outside the scope of this transaction as described.
Rendering of a truck and car charging station with a solar canopy and an adjacent solar array
Rendering of the truck charging station (not a photo): truck charging bays under a solar canopy and car charging bays under a circular canopy. Image: STRABAG press release 2026-11-13, credited on the page to Doris Irlbacher / eLoaded
STRABAG SE has annual output of about EUR 20 billion, including about EUR 4 billion from transport and road construction in Germany
hundred million euros · annual output value · as stated in company press release
Source: STRABAG press release 2026-11-13, company profile
▸ STRABAG SE has about 89,000 employees; STRABAG AG's transport infrastructure business has about 15,000. Neither press release gives R:loaded's revenue or headcount.
02 / lot

Lot 4 and the first tender round

Commissioned by the Federal Ministry of Transport, Autobahn GmbH awarded contracts on Jun 30, 2026 for the planning, construction and operation of 124 unserviced rest areas in five lots. The consortium of STRABAG, eLoaded and R:loaded is called STRA-loaded.

Round one: 124 sites in 5 lots; lot 4 has 25 sites
Sites · unserviced motorway rest areas · awarded 2026-06-30
Source: German Federal Ministry of Transport, 2026-07-02
▸ 25 + 24 + 26 + 25 + 24 = 124. The Federal Ministry of Transport says the lot structure ensures charging stations are evenly distributed nationwide, and awarding them to several companies is meant to strengthen competition. Lot 4's sites are in southern and western Germany.
Disclosed charging points: 195 in Lot 5, 148 in Lot 2, 140 in Lot 4
Count · published by each winning bidder · lots 1 and 3 not published separately
Sources: STRABAG press release; electrive.net 2026-07-01; total difference calculated by AutoMusic
▸ 836 − 195 − 148 − 140 = 353, the combined total of 51 sites in lots 1 and 3. 140 ÷ 836 ≈ 16.7%: lot 4 accounts for 20.2% of the 124 sites.
Average charging points per site: lot 4 5.6, first round overall 6.7
Per site · charge points ÷ sites
Source: as left; averages calculated by this page
▸ 195 ÷ 24 ≈ 8.1, 148 ÷ 24 ≈ 6.2, 140 ÷ 25 = 5.6, 836 ÷ 124 ≈ 6.7. The number of charging points at each site is set individually by the federal government; winning bidders cannot add or remove any.
First round: 836 charging points, 447 MCS and 389 CCS
Units · by charging standard and power · CCS400 and CCS100 denote 400 kW and 100 kW
Source: German Federal Ministry of Transport 2026-07-02, 2026-09-15
▸ 447 ÷ 836 ≈ 53.5%. MCS and 400 kW CCS serve en-route charging, and 100 kW CCS overnight charging. STRABAG's press release in month 9 put MCS at Lot 4 at up to 2,500 kW.
Lot 4: completion planned for 2030, operated by R:loaded until mid-2034
Diagram · division of roles and timeline among the three parties
202420262028203020322034 Tenders and bids Tender 2024-09, award 2026-06-30 STRABAG · Construction Completion planned for 2030 eLoaded · system supply and planning R:loaded · operations and site management Operating contract runs to mid-2034
Source: STRABAG press releases 2026-09, 2026-11-13; German Federal Ministry of Transport 2026-07-02; bar start and end points are illustrative
The press release gives only two dates: completion in 2030 and operation until mid-2034. Start of construction and commissioning dates for individual sites have not been published; the operating bars in the chart starting from 2027 are illustrative only. From award to contract end is about 8 years. The award came in Jun 30, and the R:loaded equity transaction closed in Sep 30.
03 / Contract winner

Winning bidders for the five lots

Each of the five lots went to a single winning bidder, and every contract covers planning, construction and operation. The winners' shareholders include construction and concession groups, energy companies and service area operators.

Winners and scale of the 5 lots in the first round
Awarded 2026-06-30 · charge point counts as published by each company
LotAwardeeShareholders or membersSiteCharging points
1eliso Voltix ChargingPart of France's VINCI Concessions; eliso acquired in 2022, Voltix set up by VINCI in 202325Not disclosed
2autostrom.plusLed by Drees & Sommer, Enercity, Q1 Energie; other members include Pohl Group, RheinEnergie and others24148
3Electric Mobility Infrastructure DeutschlandGerman subsidiary of Engie Vianeo, part of France's Engie Group26Not disclosed
4STRA-loaded consortiumSTRABAG、eLoaded、R:loaded25140
5E.ON Drive & mblty consortiumE.ON Drive Infrastructure; mblty is a brand of motorway service operator Tank & Rast24195
Source: German Federal Ministry of Transport, 2026-07-02; electrive.net, 2026-07-01
▸ Of the 195 charging points in lot 5, 101 are MCS; the first station is scheduled to open from 2027, with the two companies each responsible for half the sites. autostrom.plus gives an implementation period of 2026 to 2030.
Vinci, Hochtief and STRABAG as operators in Germany's federal charging tender
Construction group · operator · relationship between the two
Construction groupTendersOperatorRelationship
VINCITruck fast-charging network, lot 1, 2026eliso Voltix ChargingGroup subsidiary
HOCHTIEFTwo regional lots of the passenger car Deutschlandnetz, 2023EWE Go HOCHTIEF LadepartnerJoint venture set up for the project by Hochtief and EWE Go, a subsidiary of energy company EWE
STRABAGTruck fast-charging network, lot 4, 2026R:loadedConsortium partner at bidding; STRABAG has held 50% since 2026-09-30
Source: electrive.net 2026-07-01; GÖRG 2023-10-04; HOCHTIEF press release 2024-08-06; STRABAG press release 2026-11-13
▸ HOCHTIEF's bidding entity is HOCHTIEF Ladepartner; the two regional lots it won each have more than 400 charging points. HOCHTIEF says the two partners handle planning, construction, financing and operation. The passenger car Deutschlandnetz comprises 23 regional lots, with about 1,000 sites and about 8,000 fast-charging points network-wide.
04 / Second round

Scale and terms of the second tender round

Sites with service areas were not included in the first round. Autobahn GmbH published a project prospectus in month 9; the conditions below come from electrive's report on that prospectus and may change once the tender documents are formally published.

About 3,300 charge points in the second round, 836 in the first
Count · MCS and CCS · round two figures are approximations from the project brief
Source: German Federal Ministry of Transport, 2026-07-02; electrive.net, 2026-09-18
▸ About 1,300 + about 2,000 = about 3,300, roughly 3.9 times 836. MCS accounts for about 53.5% in the first round and about 39.4% in the second. The Federal Ministry of Transport's network-wide target is about 1,800 MCS and about 2,400 CCS points, about 4,200 in total.
Federal truck fast-charging network of about 350 sites: 124 awarded, about 225 still to be tendered
1 sites per square · without and with service areas
Lot 4: 25 sitesRemaining 99 sites in round oneApprox. 225 sites with service areas
Source: German Federal Ministry of Transport, 2026-09-15
▸ The Federal Transport Ministry cites about 225 sites, the project specification 227; this chart uses 225 cells. Tank & Rast operates more than 90% of Germany's sites with service areas; these were left out of the first round due to litigation between Fastned and Autobahn GmbH.
Average chargers per site: 6.7 in round one, about 14.5 in round two
Per site · charge points ÷ sites
Source: as above; averages calculated by this page
▸ 836 ÷ 124 ≈ 6.7, 3,300 ÷ 227 ≈ 14.5; the latter is about 2.2 times the former. The second round is split into five overlapping regional lots of about 45 sites each, averaging about 650 charging points per lot.
Round two tender termsAutobahn GmbH project brief · reported by electrive.net 2026-09-18
Contract scope
Planning + construction + operation
Bundled tender, as in round one
Contract term
Year 8
Extendable by up to 4 years
Construction period
Year 5
Depends on whether grid connections arrive on time
Lot
5 items
About 45 sites each; service areas on opposite sides of the motorway belong to the same lot
Award cap
1 lots each
Bids allowed on all lots, unless no other qualifying bid is received for a lot
Planned start
Nov 2026
Timeline as listed in the tender specifications; grid connection costs borne by the federal government
Source: electrive.net 2026-09-18 (Autobahn GmbH project brief)
Second-round evaluation: price 70%, quality 30%
% · award weighting
Source: electrive.net 2026-09-18
▸ Minimum charge-point power is also set: at least 1 MW for MCS, at least 400 kW for CCS en-route charging and at least 150 kW for CCS overnight charging. The tender keeps the "power pass-through" model, so logistics companies can bring their own electricity contracts when charging.

Calculating both rounds' figures together

Lot 4 has 140 charging points, 16.7% of the 836 in the first round and 3.3% of the roughly 4,200 across the whole network.

In the second round, each lot has about 45 sites, averaging about 650 charging points, or 4.6 times the 140 in lot 4.

The federal government has allocated around EUR 1 billion for the entire network, which works out to roughly EUR 240,000 per charging point across about 4,200 points. Grid connection costs are borne separately by the federal government, and this per-point average does not represent the contract value of any individual lot.

From the passenger car Deutschlandnetz to round two of the truck fast-charging network: Sep 2023 to Nov 2026
Tender, award and deal milestones
2023-09
Deutschlandnetz regional lot awards for passenger cars
A consortium of HOCHTIEF Ladepartner and EWE Go won two regional lots, and the partners set up a joint venture for the purpose.
2024-09
Federal government tenders truck charging at rest areas without services
First time such a tender mandates the "power pass-through" model.
2024-11-28
STRA-loaded announces joint bid
R:loaded, eLoaded and STRABAG form a consortium.
2026-06-30
Autobahn GmbH awards five lots
124 sites, 836 charging points; STRA-loaded won lot 4.
2026-09-15
Federal Transport Ministry announces implementation phase
The five winning bidders have begun site-by-site planning; Autobahn GmbH says grid connection applications began in 2024.
2026-09-30
R:loaded 50% stake closed
econX. capital transferred to STRABAG AG; Oliver Nee steps down.
2026-11-13
STRABAG announces stake
Says it can now offer integrated solutions for public tenders and for industrial and logistics customer projects.
2026-11
Second tender round planned to launch
227 sites at staffed service areas; no reports of an official launch as of Nov 14.
Data quick reference
Figures · definitions · sources
FiguresScopeSource
50%R:loaded SE stake acquired by STRABAG AG; the remaining 50% is held by eLoadedSTRABAG 2026-11-13;electrive 2026-11-14
2026-09-30Closing dateeconX. capital press release
25 sites / 140 unitsRest areas without services and truck charging points in lot 4STRABAG 2026-11-13
2030 / mid-2034Planned completion of lot 4; end of R:loaded operating contractSTRABAG 2026-09、2026-11-13
124 sites / 836 unitsSites and charging points in the five first-round lots; MCS 447, 400 kW CCS 157, 100 kW CCS 232Federal Ministry of Transport 2026-07-02
195 / 148Charging points in lot 5 and lot 2electrive 2026-07-01
Approx. 350 sites / approx. 4,200 pointsPlanned sites and charge points of the federal truck fast-charging network; around EUR 1 billion in federal fundingFederal Ministry of Transport 2026-09-15
227 sites / approx. 3,300 unitsRound two sites with service areas: about 1,300 MCS plus about 2,000 CCSelectrive 2026-09-18
8 years + 4 yearsSecond-round contract term and maximum extensionelectrive 2026-09-18
70% / 30%Price and quality weighting in second-round evaluationelectrive 2026-09-18
Approx. EUR 4 billion / approx. EUR 20 billionAnnual output of STRABAG AG's transport infrastructure business and of STRABAG SESTRABAG 2026-11-13
Sources: see each row. Averages, shares and multiples calculated on this page.
Note on sources: the total number of charging points in the first round follows the 836 given in the body text of the Federal Ministry of Transport (447 + 157 + 232); the summary box on the same page says 824, and STRABAG's English press release of month 9 says 863; this page does not use those figures. The second-round conditions come from media reports on the project description, not the original tender documents. The acquisition price, R:loaded's revenue and the contract value of lot 4 have not been disclosed. The rendering at the top of the page is a press release image, not a completed site.