Spain · Local production by Chinese automakers · Financing and supply chain Expansión 2026-11-05 · Economía Digital 2026-11-02

Ebro secures RMB-denominated loan of up to €200 million from China Exim Bank: Geely says European production costs are 70% to 100% higher than in China

Ebro, the Spanish carmaker whose plant company Chery holds a stake in (the plant is in Barcelona's Zona Franca), announced on Nov 5 that it had signed a financing contract with the Anhui branch of the Export-Import Bank of China. The contract is denominated in renminbi and is worth up to the equivalent of EUR 200 million. It will fund a new paint shop and new production lines. Geely Auto chairman An Conghui, answering a question from Spanish outlet Economía Digital on the third-quarter earnings call, said costs in Europe could be 70% or even 100% higher than in China. For Geely's plant at Almussafes, Valencia, the first choice is Chinese suppliers that already supply Geely, though local companies are not ruled out. How many production steps the two plants will carry out locally in Spain, and how many local parts they will use, remains undecided ahead of their start of production in 2027–2028.

Expansión · 2026-11-01 / 11-05 Ebro announcement (Europa Press) · 2026-11-06 Economía Digital · 2026-11-02 La Tribuna de Automoción · 2026-07-22 ICEX Invest in Spain · Somos Eléctricos
Ebro loan ceiling (estimate)
0 million EUR
Priced in RMB, converted at exchange rate
Fixed rate
0%
10-year term, including a 3-year grace period
Geely says European costs are higher by
0%
Quote: 70% or even 100%
Geely's stake in the joint venture
0%
Ford holds 66%, Almussafes plant
01 / Financing

Loan terms: 10-year tenor, 3-year grace period, 2.65% fixed rate

Expansión was first to report the financing on Nov 5, and Ebro issued a statement the next day confirming the term, grace period, interest rate and first drawdown amount. The lender is the Anhui branch of the Export-Import Bank of China, and the borrowers are two subsidiaries, Ebro SUV and Ebro Factory. Ebro has also signed a guarantee agreement with the Export-Import Bank covering 60% of the financing.

Ebro financing contract with the Export-Import Bank of ChinaExpansión 2026-11-05; Ebro announcement 2026-11-06
Cap (estimate)
€200 million
Signed in RMB; euro amounts are estimates
Term
Year 10
Incl. 3-year grace period
Interest rate
2.65% fixed
Fixed for full term
Expected first drawdown
About 35 million euros
Remainder drawn down in tranches as the production line is built
Guarantee contract coverage
60%
60% of the financing, signed alongside the loan
Use
Paint shop + new production line
New paint shop (P2) and export-oriented production lines
Source: Expansión 2026-11-05; Ebro announcement via Europa Press 2026-11-06; Ara 2026-11-06
Ebro loan structure: capped at €200 million, with a first drawdown expected at about €35 million and the remaining €165 million still to be drawn
EUR million · 165 million = 200 − 35
Source: Expansión 2026-11-05; "to be drawn" figures are our own conversion
▸ The first tranche is about 17.5% of the cap; if fully drawn for a year, interest would be about EUR 5.3 million. The loan is denominated in RMB, so actual costs when repaid in euros will vary with the exchange rate.
Ebro first-half losses: EUR 18.8 million in 2025, EUR 8 million in 2026
EUR million · H1 2026 consolidated revenue EUR 309.7 million, +194% YoY
Source: Expansión 2026-11-01
▸ Losses narrowed to €8 million; 13,393 registrations in Spain in H1, a 2.2% market share.
Ebro Factory shareholding: Chery holds 40%
% · Ebro Factory is the company operating the Zona Franca plant
Source: Expansión 2026-11-01
▸ One of the borrowers is this plant company, 40% owned by Chery.
02 / Process

Body and paint shop reshoring: bodies are currently welded and painted in China; this moves to Barcelona from Q1 2027

La Tribuna de Automoción reported in month 7, citing industry sources, that the M1 line currently assembles components onto bodies welded and painted in China; welding and painting, originally scheduled to start in Oct 2026, have been postponed to Q1 2027. According to Expansión, the s400, Jaecoo 5 and s700 are then expected to start local body welding, bringing all Zona Franca production areas into use; the delayed launch of Jaecoo models has led Ebro to readjust its spending.

Zona Franca plant timeline: Nissan exits end-2021, welding planned to start in Q1 2027
Sorted by report date
End of 2021
Nissan exits Barcelona plant
Former Nissan Zona Franca plant ceased production.
Nov 2024
Ebro officially starts vehicle production at the original plant
Cumulative output of 17,308 units by end-2025.
Jul 2026
Body and paint shops postponed to Q1 2027
Originally scheduled for Oct 2026; Jaecoo 5 and Omoda 5 pushed back accordingly.
Nov 5, 2026
Signed financing contract with the Export-Import Bank of China
Up to EUR 200 million for a paint shop and new production lines.
Q1 2027 (planned)
s400, Jaecoo 5, s700: local body welding expected to begin
All production areas are in operation; there are also plans to build a BEV based on the Chery QQ3.
Source: Expansión 2026-11-01 / 11-05; La Tribuna de Automoción 2026-07-22
▸ About two and a half years from groundbreaking to planned start of welding, with body-in-white and paint delayed once along the way.
Process locations for the Zona Franca plant: welding and painting currently in China, final assembly in Barcelona
Compiled from reports · "Planned" means from Q1 2027
ProcessCurrentFrom Q1 2027 (planned)
Body weldingChinaBarcelona
PaintingChinaBarcelona (new paint shop)
Component assembly / final assemblyBarcelona lines M1 and M0Barcelona
S700 partsShipped from China for nowNo plan given in reports
First fully produced modelS700, replacing the originally planned S400
Source: La Tribuna de Automoción 2026-07-22 (citing industry sources); Expansión 2026-11-05
▸ Only once the new paint shop is in operation will bodies stop arriving as finished bodies and instead be welded and painted in Barcelona.
Ebro Zona Franca output: 17,308 units from Nov 2024 to end-2025, 16,000 in H1 2026, about 40,000 tentatively planned for 2027
Units · 2027 figure from union sources, not confirmed by the company
Source: Expansión, 2026-11-01 (2027 plan: 30,000 units on the M1 line, 10,000 on the M0 line)
▸ About 33,000 units cumulatively as of June this year; the union considers the 40,000-unit plan insufficient and wants entry into new markets.
Ebro s400 Plus on-road footage
Ebro s400 Plus. The s400 is one of three models expected to start local body welding in Q1 2027. Image: Ebro website newsroom
03 / Supply chain

Geely supply chain: Chinese partners first choice for Almussafes, local Valencia suppliers not ruled out

Geely Auto held its Q3 earnings call in Mandarin on Oct 29. According to Economía Digital on Nov 2, An Conghui was asked about Geely's competitive edge in going global and how overseas plants could protect margins. He said costs in Europe could be 70% or even 100% higher than in China, but "if we can connect the supply chains on both sides, costs can be kept under control." Asked what share of the car's parts would be produced in Valencia, Geely gave no figure, saying only that it would comply with local and regional requirements and adjust its approach where necessary.

Geely's stated European production cost: 170 to 200 in Europe vs 100 in China
Index (China = 100) · Based on An Conghui's statement of "70% or even 100% higher"
Source: Economía Digital 2026-11-02 (Geely Q3 earnings call Q&A); index calculated by the author
▸ Geely's response is to connect its supply chains in China and Europe, with strategic suppliers "going global with Geely" while it also works with local suppliers.
Almussafes JV shareholding: Ford 66%, Geely 34%
% · Operations start in H1 2027; from 2028 the plant will build 3 Ford models and 2 Geely EVs
Source: ICEX Invest in Spain 2026-07-29; Somos Eléctricos 2026-09-09
▸ The plant has annual capacity of nearly 500,000 units, and all 4,142 current employees will transfer to the joint venture.
Geely is contributing €221 million for a 34% stake in the joint venture; Ebro's Export-Import Bank loan is capped at €200 million
EUR million · Geely's investment implies a JV equity valuation of about €650 million
Source: Somos Eléctricos 2026-09-09; Expansión 2026-11-05
▸ The two sums are similar in size: one is an equity contribution, the other a long-term loan from a policy bank.
Two plants compared: Zona Franca plans to start welding in Q1 2027; the Almussafes JV will build Geely models from 2028
Compiled from reports
ItemEbro · Zona FrancaFord–Geely · Almussafes
Role of Chinese companiesChery holds 40% of Ebro FactoryGeely holds 34% of the joint venture
FundingExport-import bank loan of up to EUR 200 millionGeely invests EUR 221 million
Key milestonesBody and paint shops in Q1 2027Operational in H1 2027, production starts 2028
Supply chain statementsS700 parts temporarily shipped from ChinaPreference for Chinese partners already supplying Geely; local suppliers not ruled out
Local parts contentNot reportedGeely did not disclose the share
Source: Expansión; La Tribuna de Automoción; Economía Digital; ICEX; Somos Eléctricos
▸ Femeval, the Valencian metal industry federation, has publicly urged Geely to use local automotive suppliers.