Electroway · Magna Park Lutterworth · electric HGV charging hub opened 2026-10-14

UK's largest electric heavy truck charging hub opens: 32 charging bays sharing 2.4 MW

Electroway, at Magna Park logistics park in Leicestershire, England, officially opened on Oct 14. It has 180 secure parking spaces and 32 DC fast-charging bays, with 32 Kempower charging points installed in phase one, up to 400 kW per connector. Charging starts at 39 pence/kWh. Infrastructure fund GSIM provided the funding, Keoma Energy developed the site, and Bosch Road Services handles technical operations. The first site used no government grants. The site has 2.4 MW installed; at 400 kW per connector, up to 6 vehicles can charge at full power at once.

Kempower investor release · 2026-10 Logistics Matters · 2026-10-14 bk World · 2026-10-23 Fleet News · Driving ZEV · Green Fleet
Site-wide installed charging capacity
0 MW
Kempower system shares power dynamically across 32 charging bays
Maximum vehicles charging at full power simultaneously
0 units
2,400 kW ÷ 400 kW = 6, calculated on this page
Secure parking spaces / DC charging bays
0/ 32
Connectors to expand to about 180 in future, matching the number of bays
Charging from
0p/kWh
Milence Immingham default price 39.9p (excl. VAT)
01 / Power allocation

32 charging bays share 2.4 MW; up to 6 vehicles at full power

Kempower's published specs: 2.4 MW of installed capacity across the site with dynamic allocation, up to 400 kW per connector, and a 45-minute break adding about 300 kWh, or up to about 150 miles of range (depending on vehicle model and configuration). bk World puts the rated range of its charging bays at 150 to 400 kW, with MCS fitted as needed. Phase two will be installed early next year and is planned to add megawatt charging of up to 1.2 MW.

Electric tractor units parked at charging bays on Electroway's opening day
Image: Kempower (via FleetPoint, 2026-10)
Electroway Magna Park charging bays and electric heavy trucks
Image: Kempower. Shown are electric trucks including the Volvo FH Electric and Mercedes-Benz eActros 400; the chargers stand on yellow-and-black crash-protection bases, with bay numbers painted on the ground.
2.4 MW averaged across occupied charging bays: 400 kW per bay with 6 bays, 75 kW per bay with 32 bays
Average power available per charging point · kW · calculated as 2,400 kW ÷ occupied points, capped at 400 kW per connector
Source: Kempower investor announcement (2.4 MW, 400 kW, 32 connectors) · Average power calculated by us; actual allocation varies with vehicle battery state and charging curve
▸ Adding 300 kWh in 45 minutes works out to an average power of 300 ÷ 0.75 = 400 kW, i.e. full power throughout. On this configuration, only the first 6 vehicles charging simultaneously can reach the advertised figure.
6 of 32 charging bays can draw 400 kW at the same time
Each cell represents one charging bay · 32 in phase one · Two allocation scenarios for 2.4 MW
Scenario 1: all at full power 6 × 400 kW = 2,400 kW
Scenario 2: fully occupied32 × 75 kW = 2,400 kW
400 kWAverage 75 kW idle or not allocated power
Sources: Kempower investor announcements; Logistics Matters 2026-10-14 · Both scenarios are illustrative calculations based on installed capacity and do not represent the site's actual dispatch strategy
▸ The operator has not disclosed its battery storage capacity. bk World says the site has solar PV and battery storage, operating as one system together with high-power charging, security and access control. Public information gives no figure on whether storage can supply power beyond 2.4 MW at peak times.
Electroway Magna Park from planning to phase two: Jan 2026 to early 2027
Key milestones · station operator and partner announcements, trade media reports
2026-01
Project announced: phase 1 with 32 MCS-ready charging points and 179 articulated bays
GSIM builds, owns and operates the site in partnership with Keoma; originally due to open in Sep 2026.
2026-10-14
Officially opened
32 charging bays, about 180 secure parking spaces, 2.4 MW installed capacity, from 39p/kWh.
2026-10-20
Electroway unveils national network plan
Keoma targets 30 UK sites, with total investment approaching £1 billion once fully built out.
Early 2027 (planned)
Phase two: megawatt charging added
Up to 1.2 MW per connector; total installed capacity of phase two not disclosed.
Long term (no set date)
Connectors expanded to about 180
Matches the number of parking spaces; Keoma also plans to open about 20 similar sites over the coming years.
Sources: The Energyst 2026-01; Logistics Matters 2026-10-14; Kempower investor release 2026-10; The EV Report citing Oct 20 announcement
02 / Pricing and funding

From 39p, a 0.9p difference from Milence's default price

Milence is a joint venture of Daimler Truck, Traton and Volvo Group. Its first UK site is at Able Humber Port in Immingham, with 8 CCS bays in phase one, up to 400 kW per connector, and a default tariff of GBP 0.399/kWh (excluding VAT). The 39p published by Electroway is a starting price; long-term contracts (over one year) can be signed at fixed rates, and reports did not state whether VAT is included.

Electroway from 39p/kWh; Milence Immingham default 39.9p
Public heavy truck charging prices · p/kWh · Milence prices exclude VAT
Sources: Logistics Matters 2026-10-14 (Electroway starting price); Fleet News (Milence Immingham default £0.399/kWh, excl. VAT)
▸ Milence's Apr 2026 fact sheet states that when a third-party provider's (eMSP) charging card is used, the provider sets the price, which may differ from the base price. Both companies publish base prices only; what fleets actually pay depends on their contracts.
At 39p, a 300 kWh charge costs about £117, or about 78p per mile
Cost breakdown of a 45-minute charge · GBP · Calculated on Kempower's basis (300 kWh ≈ 150 miles)
Source: Kempower investor announcement (300 kWh, 150 miles); Logistics Matters (39p) · 117 = 300 × 0.39, 0.78 = 117 ÷ 150, calculated on this page
▸ Energy use of about 2 kWh per mile, from 300 ÷ 150. Kempower notes range depends on model and configuration, and differs significantly between a 44-tonne full load and half load.
Bays at UK public heavy-truck charging sites: Electroway 32, Milence Immingham 8, Baldock 6, Exeter 4
Heavy truck charging bays at opening · count · eFREIGHT 2030 is a depot, not a public station
Sources: Kempower investor releases; Fleet News (Milence); Driving ZEV, 2026-01-28 (Gridserve); Green Fleet, 2026-01-19 (eFREIGHT 2030)
▸ eFREIGHT 2030 has 6 bays at Kuehne+Nagel's site at East Midlands Gateway, sharing one HyperCharger rated at up to 1 MW. It will initially serve 12 electric heavy trucks, also with power shared across multiple bays.
Public charging sites usable by electric trucks, mid-2025: UK 5, Germany 50
Public sites able to charge electric trucks · count · mid-2025
Source: Driving ZEV, 2026-01-28
▸ In Jan 2026, Gridserve opened its first public motorway sites at Extra Baldock on the A1(M) and Moto Exeter on the M5, with five more planned that year at Tamworth, Thurrock, Leeds, Chester and Strensham North.
Two funding sources for public heavy-truck chargingLogistics Matters 2026-10-14; Driving ZEV 2026-01-28; Logistics Manager (first ZEHID annual report); GOV.UK 2026-03
Government grant for Electroway's first site
0 GBP
Funded by GSIM, developed by Keoma, operated by Bosch Road Services
Keoma national network target
30 sites
Total investment approaching £1 billion once fully built out; replication in Europe under consideration
DfT ZEHID demonstration programme
GBP 200 million
Four projects; around 300 vehicles and 70 infrastructure sites expected by end-2026
Electric Freightway government funding
GBP 62.7 million
Led by Gridserve; over £100 million including consortium match funding, targeting 200 chargers by 2030
Zero-emission trucks deployed by ZEHID
240+ units
Three projects in operation, more than 40 charging sites, over 2.2 million miles driven
Additional depot charging plans
GBP 170 million
Announced Mar 2026; up to £1 million per project, covering up to 70% of costs
Source: Logistics Matters 2026-10-14; Driving ZEV 2026-01-28; Logistics Manager (first ZEHID annual report); GOV.UK 2026-03
03 / Site locations

Logistics park with about 50 warehouses, ringed by the M1, M6 and M69

Magna Park is managed by Marq Logistics, with more than 13 million sq ft of floor space and tenants including Amazon, ASDA and Marks & Spencer. Kempower says hundreds of freight drivers enter and leave the park every day. The site is designed to TAPA PSR Level 2 security, with Bosch providing number-plate recognition, surveillance and remote monitoring; the driver area has a lounge, showers, laundry and a vehicle wash.

Volvo FH Electric parked at an Electroway charging bay
Image: Kempower (via FleetPoint, 2026-10)
Volvo FH Electric at an Electroway charging bay
Image: Kempower. Left, a dual-connector charger with an instruction sign; right, a MAN eTGX electric tractor unit.
Magna Park and Electroway site conditionsKempower investor announcement; bk World 2026-10-23; Logistics Matters 2026-10-14
Logistics park warehouse
About 50
Amazon, ASDA, Marks & Spencer and others
Park-based companies with existing net-zero targets
Approx. 40%
Denominator: site tenants
Coverage within a 4.5-hour truck drive
approx. 85% of population
Denominator is UK population, bk World basis
UK HGV parking space shortfall
About 11,000
As cited by Logistics Matters
Smart surveillance cameras
78 items
Plus access control, fencing, number-plate recognition and 24-hour remote monitoring
Driver showers
11 items
bk World rest area open 24 hours, plus 2 washing machines
Sources: Kempower investor releases; bk World, 2026-10-23; Logistics Matters, 2026-10-14
Comparison of UK public and demonstration heavy-truck charging sites
Specifications announced at opening · blank = not disclosed
SiteType / locationCharging baysMax power per connectorBase electricity rateFunding
Electroway Magna ParkPublic truck stop inside a logistics park · Leicestershire32 (180 parked)400 kW; 1.2 MW in phase twoFrom 39pPrivate capital, no government subsidy
Milence ImminghamPublic port-area station · A1808400 kW; MCS added in phase two39.9p (excl. VAT)Truck maker joint venture
Gridserve Extra BaldockMotorway services · A1(M)6ZEHID · Electric Freightway
Gridserve Moto ExeterMotorway services · M54ZEHID · Electric Freightway
eFREIGHT 2030 East Midlands GatewayCompany depot · Kuehne+Nagel61 MW sharedZEHID · led by Voltempo
Sources: Kempower investor releases; Logistics Matters, 2026-10-14; Fleet News; Driving ZEV, 2026-01-28; Green Fleet, 2026-01-19
▸ Electroway has 4 times as many charging bays as Milence Immingham, with the same maximum power per connector. Operators can book a specific charger and guaranteed power through the Bosch platform. It is the first UK site on the Bosch network to combine truck parking with charging.
04 / Source

Data sources for this page

SourceData used
Kempower investor release (2026-10)180 parking bays, 32 charging bays and connectors, about 180 connectors long term, 2.4 MW, 400 kW, 300 kWh in 45 minutes, 150 miles, phase two 1.2 MW, about 50 warehouses, about 40% of tenants with net-zero commitments
Logistics Matters(2026-10-14)Opening date, prices from 39p, no government funding, 30 sites and nearly £1 billion, booking a specific charger, 78 cameras, TAPA PSR Level 2, parking shortfall of about 11,000 spaces
bk World(2026-10-23)Charging points rated 150–400 kW, fixed pricing under long-term contracts, solar PV and storage, 85% population coverage, showers and laundry facilities
Fleet NewsMilence Immingham: 8 bays, 400 kW, standard price £0.399/kWh (excl. VAT)
Driving ZEV(2026-01-28)6 heavy truck bays at Baldock, 4 at Exeter; by mid-2025, 5 public sites in the UK and 50 in Germany; ZEHID £200 million, Electric Freightway £62.7 million
Green Fleet(2026-01-19)eFREIGHT 2030 East Midlands Gateway: 6 bays, 1 MW, 12 electric heavy trucks
Logistics Manager (first ZEHID annual report)240+ zero-emission trucks, 40+ charging sites, 2.2 million miles; around 300 vehicles and 70 sites by end-2026
GOV.UK(2026-03)Depot charging scheme gets an extra GBP 170 million: up to GBP 1 million per project, covering up to 70% of costs
The Energyst(2026-01)Phase 1: 32 MCS-ready charging points, 179 articulated bays, originally scheduled to open Sep 2026